BLOGGER PARADO
posted by WASHINGTON PACANHA LOTFI 1:15 PM
88º DIA - CONSTRUÇÃO DO MURO
posted by WASHINGTON PACANHA LOTFI 10:13 PM
![]()
58º DIA - TÉRMINO DA PINTURA EXTERNA E INÍCIO DO MURO LATERAL DIREITO
posted by WASHINGTON PACANHA LOTFI 5:27 PM
![]()
![]()
55º DIA - INÍCIO DA PINTURA EXTERNA
posted by WASHINGTON PACANHA LOTFI 2:34 PM
![]()
![]()
53º DIA - APLICAÇÃO DE TEXTURA E COLOCAÇÃO DO PISO DAS VARANDAS
posted by WASHINGTON PACANHA LOTFI 12:38 PM
![]()
![]()
52º DIA - COLOCAÇÃO DO PISO DAS SALAS DE ESTAR E DE JANTAR
posted by WASHINGTON PACANHA LOTFI 2:04 PM
![]()
51º DIA - INÍCIO DA COLOCAÇÃO DO PISO DA SALA
posted by WASHINGTON PACANHA LOTFI 10:36 AM
![]()
![]()
50º DIA - COLOCAÇÃO DE AZULEJOS NOS BANHEIROS
posted by WASHINGTON PACANHA LOTFI 12:55 PM
![]()
![]()
![]()
![]()
44º DIA - 1ª DEMÃO DE MASSA CORRIDA 45º DIA - RECORTE DO TELHADO
posted by WASHINGTON PACANHA LOTFI 3:58 PM
![]()
![]()
42º DIA - CONTINUA A COLOCAÇÃO DOS FORROS
posted by WASHINGTON PACANHA LOTFI 6:48 PM
![]()
![]()
41º DIA - COLOCAÇÃO DA FORRAÇÃO DO TETO
posted by WASHINGTON PACANHA LOTFI 2:45 PM
![]()
![]()
40º DIA - COLOCAÇÃO DE PISOS, PORTAS E JANELAS
posted by WASHINGTON PACANHA LOTFI 2:47 PM
![]()
![]()
39º DIA - COLOCAÇÃO DE PORTAS E JANELAS
posted by WASHINGTON PACANHA LOTFI 2:42 PM
![]()
![]()
36º DIA - COLOCAÇÃO DE VEDAPREN NA SALA ÍNTIMA E TÉRMINO DO TELHADINHO DA COZINHA
posted by WASHINGTON PACANHA LOTFI 12:41 PM
![]()
![]()
35º DIA - LIMPEZA DAS MADEIRAS E NIVELAMENTO DO PISO
posted by WASHINGTON PACANHA LOTFI 1:37 PM