21º DIA - COLOCAÇÃO DO TELHADO
posted by WASHINGTON PACANHA LOTFI 4:26 PM
![]()
![]()
17º DIA - COLOCAÇÃO DO ALAMBRADO DA VARANDA DA SALA DE JANTAR E MOLDURAS DOS VIDROS
posted by WASHINGTON PACANHA LOTFI 1:03 PM
![]()
![]()
16º DIA - TÉRMINO DA COLOCAÇÃO DA MANTA TÉRMICA
posted by WASHINGTON PACANHA LOTFI 11:33 AM
![]()
![]()
15º DIA - INÍCIO DA COLOCAÇÃO DAS MANTAS PARA ISOLAMENTO TÉRMICO DO TELHADO
posted by WASHINGTON PACANHA LOTFI 10:48 AM
![]()
![]()
14º DIA - O MADEIRAMENTO DO TELHADO ESTÁ QUASE PRONTO. AMANHÃ SERÃO COLOCADOS A MANTA E AS RIPAS
posted by WASHINGTON PACANHA LOTFI 10:58 PM
![]()
13º DIA - FECHAMENTO DAS PAREDES DO 2º PISO E INÍCIO DA COLOCAÇÃO DO MADEIRAMENTO DO TELHADO
posted by WASHINGTON PACANHA LOTFI 12:20 PM
![]()
![]()
10º DIA - MONTAGEM DA ESCADA![]()
10º DIA - MONTAGEM DO 2º PISO
posted by WASHINGTON PACANHA LOTFI 12:46 PM
![]()
9º DIA - MONTAGEM DO ALAMBRADO DO 1º PISO E DA VARANDA DO 2º PISO
posted by WASHINGTON PACANHA LOTFI 1:56 PM
![]()
![]()
8º DIA - MONTAGEM DA MADEIRA DO SEGUNDO PISO VISTA LATERAL MOSTRANDO O FECHAMENTO DA ESCADA
posted by WASHINGTON PACANHA LOTFI 2:10 PM
![]()
![]()
7º DIA - COMEÇOU A MONTAGEM DO 2º PISO
posted by WASHINGTON PACANHA LOTFI 9:55 AM
![]()
![]()
5º Dia - FECHAMENTO DAS PAREDES DO ANDAR TÉRREO
posted by WASHINGTON PACANHA LOTFI 10:49 AM
![]()
A PARTE DE MADEIRA DO 1º ANDAR ESTÁ PRONTA. AGORA AS PAREDES SERÃO FECHADAS COM TIJOLO
posted by WASHINGTON PACANHA LOTFI 5:02 PM
![]()
A MONTAGEM DA ESTRUTURA CONTINUA
posted by WASHINGTON PACANHA LOTFI 9:35 AM
posted by WASHINGTON PACANHA LOTFI 6:12 PM
![]()
COLOCAÇÃO DAS MADEIRAS JÁ COMEÇOU
posted by WASHINGTON PACANHA LOTFI 6:05 PM
![]()
COLOCAÇÃO DOS MONTANTES
posted by WASHINGTON PACANHA LOTFI 12:26 PM
![]()
PINTURA COM NEUTROL PARA IMPERMEABILIZAÇÃO DOS LOCAIS QUE VÃO RECEBER PAREDES
posted by WASHINGTON PACANHA LOTFI 6:15 PM
![]()
CHEGADA DA MADEIRA![]()
AGORA A OBRA VAI FLUIR RAPIDAMENTE
posted by WASHINGTON PACANHA LOTFI 5:45 PM
![]()
SILVIA, JOÃO VICTOR (NETO) E DUDU, FILHA DO MESTRE DA OBRA
posted by WASHINGTON PACANHA LOTFI 11:38 AM
![]()
CALÇADA PARA ACABAMENTO DOS FUNDOS DA RESIDÊNCIA
posted by WASHINGTON PACANHA LOTFI 11:37 AM
![]()
LAJE DO PISO COMPLETAMENTE PRONTA
posted by WASHINGTON PACANHA LOTFI 11:34 AM
![]()
COLOCAÇÃO DA LAJE NO PISO
posted by WASHINGTON PACANHA LOTFI 11:33 AM
ALICERCE PRONTO E VARANDAS E SALA ÍNTIMA PREENCHIDAS
posted by WASHINGTON PACANHA LOTFI 3:07 PM
PREPARAÇÃO DAS SAPATAS INCRAVADAS NA PEDRA![]()
PARTE DO MATERIAL DA PEDRA RETIRADO DO TERRENO![]()
posted by WASHINGTON PACANHA LOTFI 3:03 PM
![]()
DETALHE DA REMOÇÃO DE PARTE DA PEDRA ENCONTRADA NO TERRENO
posted by WASHINGTON PACANHA LOTFI 3:01 PM
![]()
ESTA É A VISÃO DE COMO FICARÁ A RESIDÊNICA APÓS A CONSTRUÇÃO
posted by WASHINGTON PACANHA LOTFI 3:00 PM
![]()
ESTA É A ENTRADA DO CONDOMÍNIO MONTE DAS OLIVEIRAS, VISTA DE DENTRO
posted by WASHINGTON PACANHA LOTFI 10:09 PM
ESTE BLOGGER FOI CRIADO EM 02 SET 2004 PARA QUE NOSSOS AMIGOS POSSAM ACOMPANHAR A CONSTRUÇÃO DE NOSSA CASA EM VILA VALQUEIRE, NO RIO DE JANEIRO.
posted by WASHINGTON PACANHA LOTFI 3:39 PM